PTAG Presentation for CURT® Lean Project Delivery Summit on 2021, May 3rd on CII Research: Case Study – Lean management principles & their impact on successful project delivery

Bruce Burwell, PTAG’s Partner for Capital Projects, presented a session on Case Study – Lean management principles & their impact on successful project delivery at CURT Lean Project Delivery Summit. This in-depth presentation offers a good understanding of I2PD with the help of a case study and researched data.

This presentation was originally presented at CURT Lean Project Delivery Summit on May 3rd, 2021.

Interested in downloading the slide deck? Click here for Direct Download.

Presentation’s agenda:

  • Why I2PD
  • CII I2PD Phase One Research
  • Case Study
  • Big Room
  • Joint Risk Assessment & Pool
  • I2PD Cost
  • Tools & Templates
  • I2PD Critical Success Factors
  • I2PD Benefits
  • CII I2PD Phase Two Research

Overview of PTAG’s Case Study – Collaborative Contracting Schedule, Cost and Scope Improvement Using Industrial Integrated Project Delivery – I2PD

CompanyIndustryCategoryProject Budget
Major Power GeneratorHydro Electrical GenerationConstruction$115M
GoalObstaclesSolutionResults
Provide Cost and Schedule certainty while maintaining quality and safety on a major 8 year, 8 generating unit hydro power stationOperating power plant with numerous other dam safety and powerhouse projects all vying for space in a live operation environment. Four key suppliers needed to act in tight highly orchestrated time frame to reduce outage timeSelected 4 suppliers using traditional contracting methods for competitive bidding. Winning suppliers entered  into an 8 year Multi-Party agreement with owner to develop final eng, construction plans with integrated cost, schedule & risk plans7 month reduction in procurement time, 32% percent cost reduction, 36% execution schedule savings, integrated project management and trades teams, safety, quality and reporting. 100% profits at risk with shared savings

Refer the presentation for the in-depth details of this case study where we discuss the goals, obstacles, solution, process, and results.

If you would like to learn more about I2PD please contact us.